| Early 2009 | Pre-construction activities begin. |
|---|---|
| September 2010 | Excavation work related to the non-nuclear safety side of the two new units continues to progress. The 13-story module assembly building - where structural modules will be assembled prior to actual installation - has been completed. We have also made considerable progress on the erection of administrative and office buildings, training facilities, testing labs, tool shops, and warehouses. |