Timline Detail of the nuclear regulatory commission legal timeline
October 2008 NRC Issues Notice of Hearing and Opportunity to Intervene.
December 2008 Petitions filed by Interveners.
January 2009 SCANA responded to petitions.
Mid-February 2009 Atomic Safety and Licensing Board (ASLB) held oral arguments.
Late March 2009 ASLB ruled on admissibility of petitions.